Asphalt mixing plant maintenance time requirements

Asphalt mixing plant maintenance time requirements : 
1, routine maintenance; 
2, after asphalt mixing plant worked 1000 hours, should be once a small repaired for mechanical, electrical systems; 
3, after asphalt mixing plant wordke 4000 hours, should be once a medium repaired for mechanical, electrical systems; 
4, after asphalt mixing plant worked 8000 hours, shoule be once a big repaired for mechanical, electrical system. 
Preparatory work before disassembled: 
1, asphalt mixing plant 2 drivers, 4 mechanics, 1 electricians, 2 commanders, a 20 tons tire crane;
2, two 8lbs hammers, 4 Standard special wrench, a 375 and 450 movable wrench, a set of electrical tool, two belts, buckles hoisting rope, wire, sleepers and other commonly used tools. 
3, around the asphalt mixing plant should be no debris and obstructions. 
demolition steps: 
In working procedures the disassembly and installation of asphalt mixing plant are contrary, that is the last installed part fist taken part, first installed last taken part, in the demolition process must not be careless , to prevent accidents , car crane disassembly of this project parked on flat ground, and used skid pad level.
make the system disconnect the power, remove the screw that standard section parts connected, then hanged one bye one accroding to the order; Not simultaneously loosened up and down two screw or while mobilizing two screw,Such has been the standard hanging to the ground one by one.
Demolition construction safety measures: 
1, Removal asphalt mixing plant must be in order and have someone conductor. 
2, the demolition process aerial operator should wear helmets and seat belts, the ground staff should wear helmets. 
3, when demolited the asphalt mixing plant the wind should be less than four level. 
4, the workspace is strictly prohibited non-working personnel.
DAYU Asphalt-plant is one leading supplier in road construction machinery industry in China, who is belong to LiaoYuan Group, LiaoYuan Group was established in September 1992, Headquarters is located at Henan Province, China. Dayu is asphalt plant manufacturer, asphalt plants for sale, if you are interesting our plant, please send us email machine@dayucn.biz .